As you can see work inside the house is progressing well. Plastering of the rooms, that have been fully insulated, is taking place. The first fit electrics has commenced. This means that all the fireproof wiring is being put in place for the lights, sockets, TV, Ethernet, WiFi, computers etc. The sash windows are being converted into double-glazed ones. The lift shaft is now complete and the lift has been ordered. The new wider front door is being specially made. However, we do not have enough funding for the final phases of the build. We are awaiting the results of grant applications. We may have to stop work in April until we know if we have been successful.